Thiruvananthapuram District
All social security and welfare fund board pension beneficiaries who were granted a pension before December 31, 2025, must complete the mustering process through Akshaya centres before October 31, 2026.
Audit Report 2014-15

A summary of the key details from the audit report of Manamboor Grama Panchayat (Thiruvananthapuram District) for the 2014-15 financial year is provided below:

1. General Information

Institution: Manamboor Grama Panchayat (Thiruvananthapuram District)

Audited by: Kerala State Audit Department, Thiruvananthapuram District Office

Audit Period: 16-06-2016 to 27-06-2016

President: Shri P. Suresh Kumar

Secretary: Smt. B. S. Geetha

2. Financial Overview

Opening Balance: ₹1,55,27,506

Receipts: ₹6,48,60,026

Total Availability: ₹8,03,87,532

Expenditure: ₹5,68,94,607

Closing Balance: ₹2,34,92,925

Budget Observation: The audit notes that it was not possible to reconcile the budget approved on 26-03-2015 with the annual financial statement (Single Entry vs. Double Entry). 

3. Own Revenue and Fund Utilization

Own Revenue: There was an increase in building tax and profession tax compared to the previous year (total own revenue: ₹99.57 lakh). However, there was a slight decrease in D&O license fees.

Fund Utilization: 88% of the General Sector Development Fund was utilized.

Only 54% of the SCP (Special Component Plan) fund was utilized.

Only 15% of the Performance Grant was utilized.

4. Key Audit Findings and Irregularities

A) Discrepancies in Income/Receipts (Part 2 - Income/Receipts):

Exclusion from D&O License Demand (2-1): 32 establishments were excluded from the license demand without adhering to regulations.

Omissions in the Demand Register (2-2): Certain buildings assigned new building numbers were not included in the demand register due to data entry errors in the 'Sanchaya' software (this was subsequently rectified).

Shortfall in Profession Tax (2-3): There was an under-calculation of profession tax for an official at the Sub-Registrar's Office (the amount was subsequently collected along with penal interest). Delay in processing building permits (2-4): Despite the rule requiring disposal of applications within one month of receipt, numerous permit applications were not processed within the stipulated timeframe.

b) Irregularities in expenditure (Part 3 - Expenditure):

Goat rearing project (SC women) (3-1): Beneficiaries purchased goats directly, which is against the rules; the purchase should have been made through a seven-member committee as per the guidelines.

Monitoring system (3-2): Although ₹1.95 lakh was allocated for monitoring project implementation, no project monitoring was actually carried out.

Mahatma Gandhi National Rural Employment Guarantee Scheme (3-3): Out of 1,723 cardholders, only 26 families were provided with 100 days of employment. The average number of workdays was only 57.69. No new assets were created during the year.

Puliyikkachira drinking water project (3-4): The project, completed with an allocation of ₹24 lakh from the Scheduled Castes Development Department, is currently non-functional.

Public works / Beneficiary committee works (3-6 & 3-10): Guidelines regarding the maintenance of joint bank accounts and muster rolls by beneficiary committees, as well as the requirement for approval from general body meetings, were not followed. Road asset registers and the connectivity plan have not been maintained properly.

Streetlights and water taps (3-7 & 3-8): Joint inspections were not conducted in coordination with the Water Authority and KSEB; a metering system for streetlights has not been implemented.

Ashraya Scheme (3-9): A specific project was not prepared for the mandatory Ashraya Scheme during the 2014-15 financial year.

5. Welfare Schemes

Amounts disbursed and the number of beneficiaries for various pensions provided by the Panchayat:

Widow Pension: ₹85.20 lakh (630 persons)

Old Age Pension: ₹68.89 lakh (758 persons)

Disability Pension: ₹25.03 lakh (282 persons)

Agricultural Labourer Pension: ₹14.91 lakh (203 persons)

Unemployment Allowance: ₹5.01 lakh (310 persons)

6. Audit Conclusion (Audit Certificate & Conclusion)

Subject to the deficiencies and irregularities pointed out, the Kerala State Audit Department certifies that the Annual Financial Statement of Manambur Grama Panchayat for the year 2014-15 has generally been prepared in a proper manner. However, instructions have been issued to convene a special Panchayat meeting to discuss the report within one month of its receipt and to submit a reply report addressing the discrepancies within two months.

  • Click to view the 2014-15 audit report